Student Housing

PROJECT NO. PPV-69-1001

Tenant Agency: Savannah State University
Project Location: Savannah, GA
Program Manager: Hal Gibson Companies
Project Manager: Ray Crocker
Design Professional: HADP Architecture
General Contractor: Hardin Construction Company
Project Scope: Project for construction of 683 bed Student Housing.

CONTRACT INFORMATION

Original Contract Sum: $ 23,488,809.00
Arch. Contract Date: September 27, 2010
Adjusted Contract Sum:
Through Change Order No:
Delivery Method: Design-Build
Project Size: 683 Beds

STATUS INFORMATION

Contract Completion Date: July 18, 2011 for Camilla Hubert
July 31 2011 for Phase I (buildings A & B)
December 2011 (Morgan & Adams Hall)
March 21st, 2012 for Phase II (Building C)
Anticipated Completion Date: Phase I: July 31, 2011
Phase II: March 21, 2012